Update 3/30/17

From Project Manager Todd Nash:

To date, we have mainly been clearing and grubbing the project. Water line installation began last Monday, and gas line installation is set to start this coming Monday. Graded solid rock was started today. The grading crew has been stripping topsoil and have also started placing some road fill in a few areas. All of this work, other than the clearing and grubbing, is concentrated around the beginning of the project at Firetower Road. Clearing and grubbing activities will continue to move north towards Fairfield Glade in the coming weeks until all trees within the limits have been removed.